American Airlines HDQ Central Utility Plant

Replacement of 5 cooling towers and associated 36 inch condenser water piping that services the Headquarters Campus for American Airlines. Project was delivered in two phases consisting of the following:

Phase I Pre-construction phase: Create temporary utility yard by commissioning (9) 450 ton trailer mounted air cooled chillers and (1) 500 ton trailer mounted air cooled chiller to service the air conditioning requirements of two multi-story Corporate Headquarters Buildings. These chillers were integrated into the existing building management system until final construction was completed.

Phase II Construction phase: Replace concrete roof topping and add overflow drains. Replace 36 inch condenser water piping and associated pumps. Install new VFD’s and electrical panels servicing equipment. Replace (5) 1200 ton cooling towers. Remove all temporary electrical and plumbing used during Phase I operations.